Sani Pass Upgrade
Looks like they just want to tar the approach, not the pass itself. I'm ok with that.
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
Russel Suchet, a tour operator, said: "We are extremely disappointed."
He had been a part of a concerted effort to keep the top portion of the pass gravel.
He said that the appeal of the pass was its gravel status.
Surely he got his wish then?
Please Log in or Create an account to join the conversation.
Thats what I also understood until I read this bit:
The department of environmental affairs approved the upgrading of the road as long as the final 5km stretch up the pass to the border post remained gravel.
So its a bit confusing...
Please Log in or Create an account to join the conversation.
Captain wrote: I understood the article to make reference to upgrading the entire road to the summit of the pass, probably terminating at the Lesotho border post.
From the article:
The department of environmental affairs approved the upgrading of the road as long as the final 5km stretch up the pass to the border post remained gravel.
Captain wrote: Why not fix the R74 instead?
Or both.
This is a R1b+ project (since the quoted price is always much less than the actual). But this road is used for trade between the countries and also has tourism benefits. It will naturally be tolled if tarred. I would be surprised if it is still in good condition in 10 years time though.
Please Log in or Create an account to join the conversation.
"The department of environmental affairs approved the upgrading of the road as long as the final 5km stretch up the pass to the border post remained gravel.
Mchunu said that the total cost of upgrading the 19km from Old Good Hope Trading Post to the summit of the Sani Pass at the border post would cost R887m."
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
This article brings it out a bit clearer:
www.polity.org.za/article/r887m-tarring-of-sani-pass-road-receives-ministerial-nod-2014-05-21KwaZulu-Natal Transport, Community Safety and Liaison MEC Willies Mchunu has welcomed a ruling by Environmental Affairs Minister Edna Molewa in favour of the provincial department’s upgrade of the Sani Pass road, which connects South Africa with Lesotho.
The first phase of this project had already been completed, with 14 km of the road now fully tarred.
Should there be no further appeals, construction of the remaining 5 km would begin within five months and would bring the total cost of the project to R887-million.
The upgrade of the gravel road to tar was halted when stakeholders, including local tour and lodge operators, opposed it, citing reasons to the effect that the upgrade would negatively impact on their business. The winding road up to the summit of Sani Pass attracts 4x4 enthusiasts from around the world.
Following the complaints, the Minister initially ruled in favour of the tour and lodge operators, a decision that the KwaZulu-Natal Department of Transport (KZN DoT) appealed in 2013.
The KZN DoT’s appeal was based on the importance of meeting the commitments of a memorandum of understanding (MoU) signed by the governments of Lesotho and South Africa in 2005 to improve commercial, social and economic opportunities between the two countries through increased accessibility.
Take nothing but litter, leave nothing but a cleaner Drakensberg.
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
Sani Pass road tarring goes aheadThe DoT first proposed that the Sani Pass road be tarred all the way to the 2 865-metre high summit of the pass in 2005. Phase one of the project, involving the first 14 km of road, over relatively flat terrain, was quickly approved and work began in 2006. It took six years to complete and cost R200 million.
In 2007, an environmental impact assessment (EIA) process commenced for phase two — the 19 km section to the summit. A scoping report proposed six alternatives, ranging from “doing nothing” to driving a tunnel through the top of the mountain. The KZN DoT’s preferred option was alternative five: a tarred hard surface, but no tunnel.
Following the release of the draft EIA in 2011 most of the specialist studies recommended alternative three, which called for a gravel surface together with improved road drainage.
In the final report submitted to the DEA, KZN DóT recommended the hard surface go ahead.
However, the DEA opted for alternative three and accordingly issued an environmental authorisation to that effect on July 2.
Sani gravel ‘is better’The subsequent appeal against this decision by the KZN DoT and Ezemvelo KZN Wildlife was opposed by the Southern Drakensberg Community Tourism Organisation (SDCTO) and the Sani Wildlife branch of the Wildlife and Environment Society of South Africa (Wessa).
On May 15 the DEA overturned its own decision and ruled that the tarring option go ahead.
According to Mchunu, the KZN DoT’s appeal was based on the importance of meeting commitments of a Memorandum of Understanding signed by the governments of Lesotho and South Africa in 2005 to improve commercial, social and economic opportunities between the two countries through increased accessibility between the two countries. “From an environmental perspective, it makes economic sense to upgrade the road from gravel to tar as gravel roads require regular maintenance every two years,” said Mchunu. “Furthermore, retaining the road in its gravel state will actually negatively impact the surrounding environment.”
The initial decision by the DEA was hailed by the Sani Wildlife branch of Wessa as a vindication of the EIA process. It said its reversal was “devasting news”.
In a statement issued by Russel Suchet on behalf of Sani Wildlife branch of Wessa, representing the local communities, (including the SDCTO and community tourism operators in eastern Lesotho) he said the “vast majority of these communities believed that all the specialist reports commissioned as part of the comprehensive EIA process over the past six years had shown clearly that a hard surface upgrade of Sani Pass would indeed rob our area of one of its major tourist attractions, thereby seriously damaging the tourism industry on both sides of the border”.
In the statement, Suchet said the minister had “advanced no compelling reasons as to why she has altered the well-thought out decision her own department issued last year”.
Take nothing but litter, leave nothing but a cleaner Drakensberg.
Please Log in or Create an account to join the conversation.